2026 Finish Line Production Operations Plan

Honolulu Marathon Association Events

Project Overview

Island Vision Pacific will provide finish line video production and LED display services for both the Hapalua Half Marathon and the Honolulu Marathon in 2026. Each event features a TV1 Big Screen LED Video Wall in the festival area displaying a delayed feed of runners crossing the finish line, captured by a 4K camera on a jib arm. A pre-show content loop will run on the big screen prior to switching to the delayed finish line feed.

Hapalua Half Marathon

Sunday, April 12, 2026

Production Services

LED Display

TV1 Big Screen LED Video Wall in festival area

Camera

4K camera on jib arm at finish line

Playback Delay

22-minute delayed feed to big screen

Pre-Show

Content loop before delayed feed begins

Technical Configuration

Signal Transport: Point-to-point 60 GHz AirFiber LR wireless link (~300 ft) running NDI stream from finish line to LED wall

Finish Line Power: Battery systems for camera and delay equipment

LED Wall Power: Venue-provided shore power

Schedule

Activity Timing
Setup Day Saturday, April 11 — Morning
Show Day Arrival 6:00 AM
Operational 7:00 AM

Client Responsibilities

Finish line tent (EZ UP or similar) at camera position for equipment and operator weather protection

IVP Crew Notes

Internal

Bring table, chairs, fan, and rain protection

Rigging bar and suction cups for AirFiber 60 LR mount on TV1 Big Screen

C-Stand with sandbags for AirFiber 60 LR mount near finish line

Honolulu Marathon

Sunday, December 13, 2026

Production Services

LED Display

TV1 Big Screen LED Video Wall in festival area

Camera

4K camera on jib arm at finish line

Playback Delay

30-minute delayed feed to big screen

Pre-Show

Content loop before delayed feed begins

Technical Configuration

Signal Transport: Tactical fiber optic cable run with 60 GHz AirFiber wireless bridge for final segment (~500 ft total)

Finish Line Power: Battery systems for camera and delay equipment

LED Wall Power: TV1 Big Screen onboard generator

Schedule

Activity Timing
Setup Day Saturday, December 12 — Afternoon
Show Day Arrival 3:30 AM — Roads close at 4:00 AM
TV1 Operational for Start 5:45 AM

Client Responsibilities

Finish line tent (EZ UP or similar) at camera position for equipment and operator weather protection

IVP Crew Notes

Internal

Bring table, chairs, fan, and rain protection

Bring full rigging kit for AirFiber 60 LR mounting — placement TBD onsite